Schedule Update: COVID-19

As the COVID-19 pandemic continues, we have temporarily paused Cable Remediation work in your area in effort to do our part to slow the spread of the Coronavirus. The health and safety of our customers, employees, subcontractors and the public are always our number one priority. This temporary pause will impact work that may have begun in your area or is scheduled to begin this Spring. We will post updates here on the blog for all projects in your area as this situation develops, as well as post when a project has been rescheduled.

Thank you for your patience as we continue to bring you safe and reliable electrical upgrades. Should you have any questions or concerns surrounding a project in your neighborhood, feel free to contact the coordinator below. We look forward to working in your community again soon.

 

Stephanie Power
Lead Communications Coordinator
Potelco, Inc.
253-307-5601
sjpower@potelco.net

Mercer Island: SE 71st St, Phase II Start

Good Morning Mercer Island!

Expect to see a crew working to complete Phase II of the SE 71st St (Job# 101111100). In Phase II, a Potelco crew will begin to lay the new electrical cable in the previously installed casing. Some residents may experience a necessary planned power outage between the hours of 10am – 2pm so that our crew can safely switch the power from the old cable to the new. We anticipate this portion of the project will be completed this week.

Have a wonderful day!

Bellevue: NE 13th Place, Phase I Continues

Good Morning Bellevue!

The NE 13th Place project (Job# 101116820) continues Phase I of the project this week. In Phase I, Potelco will install the protective casing underground to house the new cable along the route. You will see large vehicles and crew members in the work area. We anticipate this portion of the project to wrap up early February.

Have a wonderful week!

SCHEDULE UPDATE: Weather

Hello North King County!

Current project schedules have been delayed/altered due to weather conditions. Once crews have returned to daily scheduled work we will be sure to post updated schedule information here on the blog.  Thank you for your patience and flexibility.  If you have any questions, please don’t hesitate to post them or use the contact information provided.

Stay safe and warm!

Shammamish: NE 35th Lane, Phase I Start

Good Morning Shammamish!

The NE 35th Lane project (Job# 101115996) has begun Phase I of the project this week. In Phase I, Potelco will install the protective casing underground to house the new cable along the route. You will see large vehicles and crew members in the work area. We anticipate this portion of the project to wrap up this week.

Have a wonderful day!

Bellevue: NE 13th Place, Phase I Start

Good Morning Bellevue!

The NE 13th Place project (Job# 101116820) has begun Phase I of the project this week. In Phase I, Potelco will install the protective casing underground to house the new cable along the route. You will see large vehicles and crew members in the work area. We anticipate this portion of the project to wrap up mid January.

Have a fantastic week!

Mercer Island: W Mercer St, Phase I Continues

Good Afternoon Mercer Island!

The W Mercer St project (Job# 101111100) is continuing Phase I of the project this week. In Phase I, Potelco will install the protective casing underground to house the new cable along the route. You will see large vehicles and crew members in the work area. We anticipate this portion of the project to wrap up late December.

Have a wonderful week!

Mercer Island: W Mercer St, Phase I Start

Good Morning Mercer Island!

The W Mercer St project (Job# 101111100) has begun Phase I of the project today. In Phase I, Potelco will install the protective casing underground to house the new cable along the route. You will see large vehicles and crew members in the work area. We anticipate this portion of the project to wrap up end of November.

Have a wonderful week!

Bellevue: NE 15th St/Crossroads Apt Phase II Start

Good Morning Bellevue!

Expect to see a crew working to complete Phase II of the NE 15th St/Crossroads Apt (Job# 101101516). In Phase II, a Potelco crew will begin to lay the new electrical cable in the previously installed casing. Some residents may experience a necessary planned power outage so that our crew can safely switch the power from the old cable to the new. We anticipate this portion of the project will be completed this week.

Have a wonderful week!